Quiz on Gantt Chart of Construction Scheduling
Week1 :
1.For the Bar Chart in this diagram:
What is the work progress for activity A at the end of month 2?
A.50%
2.For the Bar Chart in this diagram:
What is the status of activity B at the end of month 2?
A.Behind Schedule
3.For the Bar Chart in this diagram:
What is the schedule status for activity B at the end of month 3?
A.On Schedule
4.For the Bar Chart in this diagram:
What is the status of the entire project at the end of month 3?
A.Behind Schedule
5.For the Bar Chart in this diagram:
At the end of month 3, what is left for activity A?
A.20%
6.The length of the bar in a bar chart, as shown in the video, represents:
A.Length of the planned duration of an activity in a construction project
7.At week 15 of the project, according to the bar chart below, what activities will be completed in the project:
A.a,b,c,d,e,f