Quiz on Activity Precedence Diagrams,Activity Relationships and Forward/Backward Passes
Week1:
Hint: Please refer to the diagram at 5:00 minutes in the video.
Ans:11
Name activity X1:
Ans:E
3.Name activity X2:
Ans:B
4.Name Activity X3:
Ans:I
5.Name Activity X4:
Ans:G
6.What is the value of X5?
Type and Integer value.
Ans:0 (zero)
7.What is the value of X6?
Type and Integer value.
Ans:5
8.What is the value of X7?
Type and Integer value.
Ans:9
9.What is the value of X8?
Type and Integer value.
Ans:12
10.What is the value of X9?
Type and Integer value.
Ans:13
11.What is the value of X10?
Type and Integer value.
Ans:18
12.What is the value of X11?
Type and Integer value.
Ans:24
13.What is the value of X12?
Type and Integer value.
Ans:19
14.What is the value of X13?
Type and Integer value.
Ans:9
15.What is the value of X14?
Type and Integer value.
Ans:5
16.What is the value of X15?
Type and Integer value.
Ans:5
17.Choose all of the relationships that are represented in a node network diagram.
Ans:Finish to Start
Start to Start
FInish to Finish
18.To determine the Early Start of an activity,
Ans:Factor in all its dependencies and see its earliest start date